Survival of the unfittest… megaprojects

UC Berkeley scholar Karen Trapenberg Frick wrote of the 25 years it took for Californians to build a Bay bridge replacement. Dr. Frick said the project was “a cautionary tale to which any governing authority embarking on a megaproject should pay heed.” British Columbia’s highly paid bureaucrats and political leaders were not paying attention.

From the news archives: Site C history

Large dams run 96 percent over budget on average, according to a University of Oxford study based on projects in 65 countries including Brazil and China. The study, published in the journal Energy Policy, showed that large dams also took about 2.3 years longer to complete than originally planned. That was about 44 percent longer than projected at the point of approval. The research was based on a study of 245 dams…

Certainty of Site C massive cost overrun is 86% (from 2014)

BC’s Minister of Energy said in mid October that the $7.9 billion budget for Site C had been examined by top international experts and was assuredly “reliable.” Two months later, Premier Clark revealed the dam budget had jumped to $8.5 billion. Days passed and when project approval was announced, the budget had jumped to $8.775 billion. Once again, the British Columbia Liberals demonstrate practiced mendacity. They are consistent though since mega-projects of the past five years typically doubled between first announcement and completion but were invariably pronounced to be on-time and on-budget. The mantra will be used again…