Budget & Estimate Disasters

Megaproject, 10 years late and 8x original budget

On April 5, 2017, Metro Vancouver awarded a contract to Acciona, a Spanish multinational conglomerate that reported 2023 revenue of about C$25 billion. The company was to build the North Shore Wastewater Treatment Plant (NSWWTP) for C$525 million. Completion date for the sewage treatment plant was 2020.

Acciona was fired by Metro Vancouver near the end of 2021. Three years later, the project is incomplete and the expected cost has risen to almost $4 billion. Metro Vancouver now hopes the plant will be operational by 2030. Bob Mackin provides a timeline of events related to the project HERE.

Acciona is one of the prime contractors on Site C, the hydroelectric project that is likely to finish at 2.5x its initial budget. The company has a troubled record:

  • Spain’s competition authority fined Acciona C$3.4 million and recommended the company be denied further contracts because of cartel behavior in road maintenance as part of public tenders of the Ministry of Development..
  • Brazilian prosecutors alleged that Acciona was involved in bribes paid to secure contracts for infrastructure projects. The company was accused of participating in a scheme where payments were made to secure favorable treatment and ensure the awarding of contracts for large projects.
  • Two high-ranking executives at Spanish builders Acciona and FCC were arrested as part of an investigation into irregular concessions at state-run water contract company Acuamed.
  • According to the World Bank, Acciona engaged in corrupt, collusive, and fraudulent conduct in order to secure a contract for a project supervising a World Bank-financed roads and airports infrastructure project in Bolivia.
  • The World Bank debarred Acciona from participating in bank financed infrastructure projects for 28 months because of corrupt, collusive and fraudulent practices.
  • Acciona and the owners of a waste-to-energy plant in Western Australia are fighting in court over a troubled project worth hundreds of millions of dollars.
  • Acciona is involved in controversy at the site of a billion dollar incinerator project near London England.

Despite problems, Acciona is popular when BC’s public officials are awarding contracts. The company is now involved in multi-billion projects in Surrey and Vancouver to extend SkyTrain. It is one of the contractors for the new Pattullo bridge and is part of the public-private partnership for renewal of Royal Jubilee Hospital.

Taxpayers should be raising hell.

Acciona is what it is, but local government officials deserve blame for the costly North Shore debacle. Not just for selecting the main contractor, but for vastly underestimating the cost and complexity of the project. Construction that takes ten years longer than anticipated and costs at least eight times more than first estimated prove serious levels of incompetence among the infrastructure managers.

Given Acciona’s track record, there might be more than human ineptitude involved.

Metro Vancouver has promised to think about an independent inquiry to look at the NSWWTP difficulties. The real need is for the province to appoint a royal commission with broad ability to investigate financial and engineering calamities affecting all BC megaprojects. The inquiry should be able to compel public officials to explain processes that result in massive cost increases and troublesome delays.


FAILING UPWARD: the idea that someone succeeds in their career despite being mediocre or incompetent.

7 replies »


  1. Quote: “Metro Vancouver has promised to think about an independent inquiry to look at the NSWWTP difficulties.”

    Where the hell is Eby on this one?

    I probably know why because Royal Commissions beget Royal Commissions.

    A few years back I inked a letter to Eby stating a need for a judicial inquiry of TransLink. It was rebuffed.

    When he became premier I updated the letter and sent it again and within 4 days I had a reply that stated; “all further correspondence with the premier must go through a provincial barrister.

    I do know what Eby is afraid of, and it isn’t pleasant. Mega projects are beset with politcal, bureaucratic and corporate corruption. Dealing with this is well above BC’s auditor General’s pay grade and the public, the taxpayer is left paying the bill.


    Here is a hint. The chief bureaucrat in Vancouver who was the biggest supporter of the Broadway subway is now earning over $700K annually as CEO of metro Vancouver. The Broadway subway is being built on a route with nowhere near the ridership to justify a subway.

    Why was this allowed to happen? A Royal Commission just might point fingers.

    Like


  2. Perhaps! if the public knew the true cost before a contract was awarded then the enthusiasm for that project would be stifled?

    The ‘trick’ for the contractor is to take the project past the too big to fail stage!


    TB

    Liked by 1 person

  3. A comment on Facebook:

    Read this and weep BC taxpayers.

    The criminality of the international engineering companies is astounding and one has to wonder WHY our governments contract with these criminal enterprises. Acciona, a Spanish multinational and the Canadian LNC Lavalin have both been convicted for illegal activities like bribery and kickbacks but that’s not all.

    They are totally incompetent as Site C and the North Shore wastewater treatment project have exposed. So why do our governments hire these crooks? This could be the standard business practices of these companies: grease the right palms and be assured of getting a multi-million dollar contract payoff.

    Like

  4. It’s passing strange that companies with a demonstrated proclivity for criminal acts in various areas of the globe all clean up their act upon entering British Columbia.

    I have the feeling Sergeant Schultz and Inspector Clouseau are minding our store.

    Liked by 1 person

    • The Association of Certified Fraud Examiners (ACFE) estimates that the median U.S. company loses the equivalent of 5% of its annual revenue to fraud and that half of the fraud cases involve collusion schemes.

      With the $4 billion (and counting) NSWWTP, that’s only $200 million. A small sum in the large universe of governments. Of course, Metro Vancouver might not be at the median.

      BC Hydro has about $9 billion passing through its hands in a year. Five percent is only $450 million. Now we should add up the spending by all levels of government and associated public agencies.

      Recalling the quote misattributed to Sen. Everett Dirkson, “A billion here, a billion there, pretty soon you’re talking real money.”

      Like

Leave a Reply to Lew Edwardson Cancel reply

Your email address will not be published. Required fields are marked *