I was recently at a meeting where North Vancouver District Council member Jim Hanson talked about the need for reform of Metro Vancouver governance. He illustrated his comments by comparing wastewater treatment projects in Victoria and North Vancouver.
The initial approved budget for Greater Victoria’s Wastewater Treatment Project, whose main component is the McLoughlin Point plant, was $765 million in 2016. The project was completed in 2020 at a cost reported by CBC to be $775 million.
Metro Vancouver’s timeline for its wastewater treatment plant:
- 2008 — Metro Vancouver purchased the site of the future North Shore Wastewater Treatment Plant at 107 Pemberton Avenue, North Vancouver.
- 2013 — The estimated project budget was in the order of $700 million.
- 2017 — The program cost was said to be $780 million with construction completion of December 2020.
- 2018 — Acciona started construction of the North Shore Wastewater Treatment Plant.
- 2021 — The estimated program cost was revised to be $1.058 billion, with a new substantial completion date of 2024.
- 2024 — The project budget was revised to an estimated $3.86 billion, with the substantial completion date in 2030.

It is no surprise that Council member Jim Hanson and his DNV colleagues are concerned. Each North Vancouver property owner will pay an extra $17,700 to cover the costs of the facility.
Categories: Accountability, Uncategorized


Believe me, taxpayers in Greater Victoria grouse about having to pay for our treatment plant, but I suppose we were lucky!