Government review of BC Hydro is specious

Some may be able to moderate use of electricity from the provincial grid but almost no individual can stop being a BC Hydro consumer. That fact obliges politicians to ensure the company is operated with maximum efficiency for the benefit of every citizen, not the relative handfull that are rewarded by BC Hydro’s misconceived spending plans. Sadly, the Horgan Government does not agree. Utility policies and company management are almost unchanged during the last 11 months and the recently announced review is specious.

Organizational inertia and Site C

The decision to proceed with Site C was not based on need for power by BC consumers. Demand is this province has been more or less unchanged since 2005… While the NDP has done much to change the direction of government in BC, they’ve been paralyzed when it comes energy policies. BC Hydro has been a troubled organization for years and it will not be rescued by timid actions. That’s bad news for every BC business and ever resident who consumes electricity.

Death knell for net metering

BC Hydro fears the amount of power fed to the grid by participants in net metering will expand substantially. As a result, this week the utility announced they intend to change the program so that it is not available to customers generating power beyond their own energy needs…

Akratic NDP

It’s easy to understand why BC Hydro argued that pushing ahead with Site C was the preferred option. A change in course would require directors and executives to admit their past decisions were colossal mistakes. Blunders that cost billions don’t help job security and do not enhance resumes…

Pushing back on Site C disinformation

Brian Cochrane’s byline is on an article about Site C published March 28 by The Tyee. The author is described as business manager of the International Union of Operating Engineers Local 115, one of the unions whose members will be working on construction of BC Hydro’s Site C dam. I was appalled by misinformation Cochrane presented — and by the publication’s fact-checking failure — and left a lengthy comment. My contribution drew approval from a some readers and a response by one diligent Site C proponent, one of 15 he left on Cochrane’s article. However, after a few hours, The Tyee removed my comment. After my inquiry, it was restored a day later…

Someone is telling us lies

When BC Liberals said the Site C completion budget was $7.9 billion, the cost of power from the project was stated to be $87 – $95 per megawatt-hour (MWh). Now, with the Site C budget up 26% to $10.7 billion, John Horgan’s NDP government claims the cost per MWh has fallen 32% to $60.

Sunk costs

Having made the wrong decision, no doubt influenced by Liberal holdovers in the civil service and BC Hydro management, it is not too late for NDP minister to choose the right course. There are many reasons to cancel Site C…

Deceit is still a BC Government tool

A BC Government “technical presentation” regarding its decision to continue construction of Site C is filled with misinformation, deceit and false justifications. If this is the quality of the advice taken by John Horgan’s cabinet on one rather important issue, we should be concerned about every other policy being considered. Apparently, if truths are inconvenient, Victoria still prefers deception.